5 big changes to expect over 5 years at the Charlotte airport
A version of this story originally ran in The Charlotte Observer.
If you’ve been to Charlotte Douglas this summer, you’ve seen that parts of it look like one big construction zone. But many critical improvements are still years away from completion, including the new terminal roadway, an expanded terminal, a fourth parallel runway, a new concourse and new control tower.
“Even if the airport didn’t grow a single bit, these projects are needed today,” Aviation Director Brent Cagle said.
Here’s a look at where the airport’s $2.5 billion, 10-year expansion plan stands, and when key projects will be completed. The projects are funded by a mix of bonds backed with airport revenues, fees charged to passengers and federal grants.
New terminal roadway
The first thing you’ll see these days when you pull in to pick up or drop off a traveler is the construction zone next to the terminal roadway. Charlotte Douglas is in the midst of a $50 million project to expand both levels of the roadway from three lanes to eight between the terminal and the hourly parking deck.
Expanded terminal and lobby
Like the opening move in a chess game, finishing the new terminal roadway will clear the way for expanding Charlotte Douglas’ lobby into the space now occupied by the current roadway. The airport’s plan is to tear down the existing road and expand the terminal and lobby outward by about 90 feet, toward the new roadway and hourly deck.
The plan also includes bridges and tunnels for pedestrians connecting the hourly deck and car rental agencies to the terminal, so pedestrians can access them without crossing the road.
Concourse A North and new gates
The airport broke ground in February on nine new gates, in addition to the 96 currently in use. Concourse A North, as the expansion is called, is adjacent to Concourse A, where the rental car agencies and parking lots used to be. The $200 million project is slated for completion in spring 2018.
A future phase of the Concourse A North expansion calls for an additional 16 gates. That $300 million project would start in 2020 and open in 2022.
New control tower
Construction on the airport’s new control tower officially kicked off last month. At 370 feet, it will be more than twice as tall as the current tower.
The $60 million project, funded by the Federal Aviation Administration, adds more room for air traffic controllers and will improve their sight lines, allowing them to oversee more takeoffs and landings and increasing safety, officials have said.
Although the tower itself should be built by 2018, installation, testing and certification of the elaborate air traffic control electronics will add at least another year to the project. Cagle said he expects the new tower to be operational by late 2019 or early 2020.
Fourth parallel runway
One of Charlotte economic developers’ abiding wishes is a nonstop flight to Asia. Cagle said the airport’s current runways, up to 10,000 feet in length, aren’t long enough to support a fully loaded plane with fuel for the long haul to China or Japan year-round. That’s one reason the airport plans to build a 12,000-foot, $422 million fourth parallel runway, between two existing runways.
The FAA, which would fund part of the cost, must approve the project, a process that Cagle said could take three years.
“We hope it doesn’t take longer, but it might,” said Cagle. Assuming the FAA’s study, currently underway by a consultant, recommends in favor of the new runway, Cagle said it could be built and operational in the early 2020s, possibly 2021.
Photos: David T. Foster III/Charlotte Observer, Charlotte Douglas International Airport
This story was originally published July 17, 2016 at 9:00 PM with the headline "5 big changes to expect over 5 years at the Charlotte airport."